    Since breaking ground in December 2010, construction crews have made steady progress on the University Center. The New School is committed to providing our university community and neighbors with regular updates throughout the building process. Check back here for updates. If you would like regular updates delivered to your email inbox, send an email to Communications and External Affairs to sign up for the quarterly “University Center Community Newsletter.”

    Construction Schedule

    • Excavate/pour foundations: 12.2.10 through 6.22.11
    • Superstructure concrete: 6.25.11 through 5.16.12
    • Topping out (completion of vertical construction): 5.18.12
    • Elevator installation: 4.17.12 through 8.1.13
    • Finishes: 4.17.12 through 11.1.13
    • Ready for occupancy: Fall 2013